About this episode
The university wanted a bridge for its students over a busy roadway that would appear intriguing from afar. Instead it collapsed before it was even finished. We look into how design errors, poor peer review and denial led to a collapse that claimed six peoples lives.With John Chidgey.This show is Podcasting 2.0 Enhanced
Report into the Incidents:
NTSB Final Report (PDF)
Design Criteria and Bid:
FIU Pedestrian Bridge Design Criteria Rev 0 (PDF)
FIU Pedestrian Bridge Design Criteria Rev 1 (PDF)
MCM / FIGG Proposal (PDF)
Civil Structural References:
Truss
Truss Bridges
Steel Bridge Design
What is Post-tensioning?
Prestressed, Pretensioned and Post-Tensioned Concrete
Engineer of Record Definition
Non-Destructive Concrete Evaluation & testing
Companies Involved:
Louis Berger is now part of WSP
WSP Global
FIGG Engineering
FIGG Bridge Engineers
Links of Potential Interest:
Florida bridge collapse has some hard lessons
Florida International University pedestrian bridge collapse
University-City Prosperity Project